State Highway 128, Wisconsin
From IHSDMDownload
User Information
Organization/Agency: Fleming, Andre and Assoc., Inc.
Basic Project Information
Project Name/Description: State Trunk Highway 128 Benefit/Cost Analysis
Nature of the Project/Study: 3R Safety Improvement
Project Location: Saint Croix County, Wisconsin, Glenwood City to State Trunk Highway 64
Highway Length: 5.4 mi
Functional Classification: Minor Arterial
Design Speed: 60 mi/h
Posted Speed: 55 mi/h
Terrain Type: Half Rolling, Half Level
Application of IHSDM
IHSDM Module(s) used:
• Crash Prediction
Purpose of using IHSDM on this project:
IHSDM was used to estimate the expected levels of crash reduction for two design alternatives as compared to a base case.
STH 128 is the worst of a group of highways with high crash rates and with a very high percentage of run-off-road crashes. Results of this study will provide the basis for a program to prioritize HES/HSIP projects in an equitable manner.
Stage(s) of the project development process in which IHSDM was applied (e.g., planning, preliminary design, final design, etc.):
Planning
How IHSDM results were used to make design decisions:
IHSDM results were used to predict the level of crash reduction of various alternatives. IHSDM provided much of the basis for the “benefit” side of the benefit-cost analysis.